| |  please, hold the mouse on the logo | Nuremberg  [metro]Country: Germany
 Line: Metro:U1
 DLM:U2, U3
 Inhabitants: City 500000, District 3500000
 
 | 
 DESCRIPTION(last modified June 26, 2018 )The construction of Nurnmberg metro took place starting from years '60s.
 The first metro line (U1) opened in 1972 (Langwasser Sud-Bauernfeindstrasse) and it was extended in 1974, 1975, 1978, 1980, 1982, 1985 and 1998; it currently runs from Langwasser Sud to Hardhohe along a partly underground track. U1 interchanges with U2 and U3 at Plarrer and Hauptbahnhof.
 The second line (U2) opened in 1984 (Plarrer-Schweinau) and it was extended in 1986, 1988, 1990, 1993, 1996 and 1997; U2 is operated as a driverless system (automated metro operations) since 2010. It interchanges with metro line U1 (see above) and it shares part of the track with U3 (Plarrer-Rathenauplatz); furthermore, U2 also interchanges with the ground level railway network (at Nordostbahnhof, Hauptbahnhof, Rothenburger Strasse and Schweinau).
 A third line (U3, first section Gustav Adolf Strasse-Maxfeld) opened on 15 June 2008; it was extended in 2011 (Maxfeld-Friedrich Ebert Platz) and 2017 (Friedrich Ebert Platz-Nordwestring). U3 is totally automated (driverless system).
 
 | HISTORY(last modified June 26, 2018 )| date | section name | line |  |  |  | 01-03-1972 | Langwasser Sud-Bauernfeindstrasse | U1 |  | 18-06-1974 | Bauernfeindstrasse-Frankenstrasse | U1 |  | 23-09-1975 | Frankenstrasse-Aufseßplatz | U1 |  | 28-01-1978 | Aufseßplatz-Weißer Turm | U1 |  | 20-09-1980 | Weißer Turm-Barenschanze | U1 |  | 20-03-1982 | Barenschanze-Jakobinenstrasse | U1 |  | 07-12-1985 | Jakobinenstrasse-Furth Hauptbahnhof | U1 |  | 05-12-1998 | Furth Hauptbahnhof-Stadthalle | U1 |  | 28-01-1984 | Plarrer-Schweinau | U2 |  | 27-09-1986 | Schweinau-Rothenbach | U2 |  | 24-09-1988 | Plarrer-Hauptbahnhof | U2 |  | 29-09-1990 | Hauptbahnhof-Rathenauplatz | U2 |  | 22-05-1993 | Rathenauplatz-Schoppershof | U2 |  | 27-01-1996 | Schoppershof-Herrnhutte | U2 |  | 27-11-1999 | Herrnhutte-Flughafen | U2 |  | 02-01-2010 | beginning of driverless operations | U2 |  | 14-06-2008 | Gustav Adolf Strasse-Maxfeld | U3 |  | 11-12-2011 | Maxfeld-Friedrich-Ebert-Platz | U3 |  | 22-05-2017 | Friedrich Ebert Platz-Nordwestring | U3 | 
 
 | (last modified June 26, 2018 )| TECHNICAL DATASingle line length (Km)
 U1:18.5
 U2:13.2
 U3:8.1
 Single line stops
 U1:27
 U2:16
 U3:13
 Single line avg. distance (km)
 U1:0.7
 U2:0.9
 U3:0.7
 Total track length (km)
 37.1
 Total network stops
 48
 Avg. stop net distance (km)
 0.80
 Type
 steel wheels
 Current/Voltage
 750 V DC (third rail)
 Guide/gauge
 standard gauge rails (1435 mm)
 Vehicles builder
 U1:--
 U2:SIEMENS
 U3:SIEMENS
 Model
 U1:--
 U2:DT1,DT2
 U3:DT3
 Operator
 VAG NURNMBERG
 
 
 (DLM = Driverless Metro)
 | 
 | 
 This image is shown smaller (800 x 541 pixels) than its maximum size (1920 x 1299 pixels)Please click on the map to enlarge it to its maximum size
 metro - nuremberg; By HerrMay [CC0], from Wikimedia Commons
 |